A Chilling Account: Hudson /York’s First-Hand Experience Recovering Gas Six Stories Below ‘Ground Zero’



NEW YORK CITY - It was one week shy of three months since the catastrophic events of September 11th at the World Trade Center and "Ground Zero" smoldered as a danger still lurked some six stories below. Known as an HVAC industry marvel, 12 giant York chillers that once cooled some 35,000 WTC occupants were left crippled and condition unknown since the two behemoth 110-story towers came crashing down on that fateful morning.

   Among the immediate safety concerns for the hundreds of rescue and construction workers at the site was the status of the refrigerant in the large chillers that lay far beneath the massive pile of broken concrete and twisted steel. The fear was that heat from inferno-like fires above may turn leaking refrigerant into a highly acidic vapor or since refrigerant weighs more than air, the chemical coolant would displace oxygen making it difficult or impossible to breathe.

   The calls quickly went out first to DuPont and York International, the manufacturer of the chillers as well as the service contractor for the World Trade Center. Both companies, in turn, called Hudson Technologies for its experience and expertise in handling the most challenging refrigerant related issues and problems. This would be no simple, straightforward recovery. Hudson has done thousands of large chiller refrigerant recovery and decontamination jobs across the country. These have included aircraft carriers, submarines and nuclear power plants, as well as large comfort cooling and process cooling systems. Hudson was called in for its engineering and chemistry knowledge, which has been a company hallmark since it was founded a decade ago.

   Within days of the collapse, several attempts were made by Ground Zero crews to reach the giant chillers, including using remote cameras, but damage to the surrounding area was too severe and dangerous. It wasn't until a full two months later that Ground Zero engineers and the Hudson/York team, fronted by New York City firefighters who,
while working in knee-high water, sledge hammered their way through concrete walls and steel doors, could reach a mechanical room and examine some of the chillers six stories down. Large slabs of concrete from above visibly crushed many of the chillers, but two others were found intact with speculation that they still contained gas.

   York International and Hudson Technologies were charged with writing the engineering specifications for the gas recovery under the supervision of the New York City Department of Design and Construction (DDC), which is overseeing all work at Ground Zero. The Hudson/York team worked closely with the Environmental Protection Agency, the Port Authority of New York & New Jersey, Bovis Construction and the DDC to develop the parameters, strategy and tactics for recovering the refrigerant found in one of the enormous chillers. Safety was paramount in the planning and every effort was made to ensure all steps were carefully calculated and all precautions taken.

   With a New York Fire Department approved emergency evacuation plan in place, Hudson rolled one of its 40 ft. tanker trucks into Ground Zero, parking it only feet away from the large upright cross made by a falling steel beam that has stood as a symbol of prayer and remembrance of the terrorist attack victims.
The Hudson/York team snaked about 700 feet of hose from the tanker down five stories to a hole in a double slab of concrete just big enough to crawl through that was created earlier by the firefighters. From there the team entered a stairway in pitch blackness and in knee high water maneuvered around broken pipes, fallen concrete and other debris and down one more flight to one of the mechanical rooms.

   The team was equipped with flashlights, but the darkness was so intense that it quickly swallowed up any light. Hooking up the hoses to the York chiller valves became as much a touch and feel as actual sight since the bottom of the chiller was submerged under water. The team described the entire experience as very eerie and chilling, and they weren't talking about standing knee-high in water and the coolness of the air. As one of the technicians recounted "the equipment room resembled a war zone cast in complete darkness."
The Hudson/York team worked over three days, Dec. 4 - 6, from 7 p.m. to 5 a.m., when excavation crews above ground were not working. The team was outfitted with detectors that measured refrigerant, carbon monoxide, hydrogen sulfide and oxygen in the air, and each carried a supply of oxygen while underground.

   The recovery was completed without a hitch as per plan. The success was attributed to the combination of York's knowledge and experience in the servicing of large tonnage chillers and Hudson's expertise in developing customized solutions to complex refrigerant-side problems including extraordinary refrigerant recoveries. The Company used its patented Zugibeast
®, an ultra-fast machine designed and developed by Hudson, to recover the refrigerant. The Hudson/York team may be called in again if other units are discovered as the excavation work continues and other mechanical rooms with chillers are made accessible.

 


 

© Copyrighted 2002 Hudson Technologies, Inc.